June 30th 2021
Work progress during the month of June 2021
June 30th 2021
Work progress during the month of June 2021
June 10th 2021
Work progress during the month of May 2021
April 26th 2021
Work progress during the month of April 2021
February 29th 2021
Work progress during the month of February 2021
January 29th 2021
Concrete reinforcement and pillars of structures.
December 17th 2020
Excavation executed at 50%
October 26 2020
Excavation executed at 50%
September 3rd 2020
May 26 2020
Demolition of basement and first floor completed. Clearing of debris in execution
May 6 2020
Views from the plot