News and progress of execution in our promotions.

May 6 2020

Views from the plot

April 29th 2020

Structure completed

April 25th 2020

Finalizing elevator boxes, accesses and storage units.

March 18th 2020

Framework finished for the first floor of blocks A, B, and C. Now in execution the framework for the first floor of block D and the framework for the rooftop of block A.

March 5th 2020

Forged ground floor (homes and common areas) finished.
Forged 1st floor of building A finished.
In execution the formwork for the 1st floor slab of building C and ground floor pillars of building B.

February 14th 2020

Construction of the basement concrete roof slabs and sanity concrete slabs, via pump for blocks A and C.

January 27th 2020

Perimeter walls completed, basement floor slab 50% completed, and the formwork has begun!

January 13th 2020

Finishing load bearing walls, plumbing framework, pillars and elevator shafts.  Swimming pool basin ready!  In a few days we start on the basement floor slab

December 20th 2019

Making more progress!

December 18th 2019

Basement and Elevator pit ready!

December 4th 2019

We are pleased to communicate that on the 19th of October we began the excavation of the Belisla Encant development, completely sold out and the first phase of our ambitious project in Ibiza

November 5th 2019

We are pleased to communicate that on the 19th of October we began the excavation of the Belisla Encant development, completely sold out and the first phase of our ambitious project in Ibiza